(A) New crossings or replacement of existing crossings, of existing roadways shall normally be accomplished by driving, jacking, tunneling, or boring under the roadway without disturbing the existing pavement, shoulder or drainage.
(B) Where unusual conditions indicate the use of another construction method, such method is subject to the approval of the County Roads Department. The use of open cut trenches in existing roadways shall be permitted only when justified to the satisfaction of the County Roads Department.
(C) The County Roads Department can require resurfacing of the roadway to a maximum of 200 feet on each side of a trench crossing a roadway.
(D) When open cut is permitted longitudinally in the roadway, resurfacing to the total width of the traveled lane(s) disturbed shall be required.
(Ord. —, passed 6-30-2009) Penalty, see § 54.99