§ 157.171 TIME LIMITS ON BOARD APPROVALS.
   (A)   Structures. A decision of the Board permitting the erection or alteration of a structure shall be valid for a period of 2 years, unless a zoning permit for such erection or alteration is obtained within this period and the erection or alteration proceeds to completion in accordance with the terms of the decision.
   (B)   Uses. No decision of the Board permitting the use of a structure or land shall be valid for a period longer than 2 years, unless the use is established within the period; except that, where such use is dependent upon the erection or alteration of a building, such order shall continue in force and effect if a zoning permit for such erection or alteration is obtained within the period, and such erection or alteration proceeds to completion in accordance with the terms of the decision.
(Ord. —, passed 5-13-1997; Am. Ord. —, passed 8-8-2000; Am. Ord. —, passed 4-30-2002; Am. Res. 2006-14, passed 10-3-2006)