§ 157.146 ZONING PERMITS.
   (A)   Hereafter, no structure (except certain signs as provided in §§ 157.105 et seq.) shall be erected, constructed, reconstructed, altered or moved; no land or building used or occupied and no land or building changed in use, until a zoning permit has been secured from the Zoning Administrator. Upon completion of changes in use and construction, reconstruction or moving of structures, the applicant shall notify the Zoning Administrator of such completion.
      (1)   No permit shall be considered as complete or permanently effective until the Zoning Administrator has noted on the permit that the work or occupancy and use has been inspected and approved as being in conformity with the provisions of this chapter.
      (2)   A use and occupancy permit proposed to be issued under a County Building Ordinance shall also be reviewed and approved by the Zoning Administrator.
   (B)   The Zoning Administrator may grant a permit for a nonconforming temporary building or use incidental to a construction project when such building or use is reasonably required for such project. Such temporary permit shall terminate at the time of completion of the project.
(Ord. —, passed 5-13-1997; Am. Ord. —, passed 8-8-2000; Am. Ord. —, passed 4-30-2002)