§ 155.070 INSPECTION SCHEDULE AND REPORTS.
   (A)   The developer shall notify the Stormwater Management Office at least 48 hours before commencing any work in conjunction with site development, the stormwater management plan and upon completion of the project when a final inspection will be conducted.
   (B)   Regular inspections shall be made and documented for each ESD planning technique and practice at the stages of construction specified in the Design Manual by the Stormwater Management Office, its authorized representative, or certified by a professional engineer licensed in the State of Maryland. At a minimum, all ESD and other nonstructural practices shall be inspected upon completion of final grading, the establishment of permanent stabilization, and before issuance of use and occupancy approval.
   (C)   Written inspection reports shall include:
      (1)   The date and location of the inspection;
      (2)   Whether construction was in compliance with the approved stormwater management plan;
      (3)   Any variations from the approved construction specifications; and
      (4)   Any existing violations.
   (D)   The owner/developer, the Garrett County Commissioners, and on-site personnel shall be notified in writing when violations are observed. Written notification by the inspector identifying the violation shall describe the nature of the violation and the required corrective action.
   (E)   No work shall proceed until the Stormwater Management Office or designated representative inspects and approves the work previously completed and furnishes the developer with the results of the inspection reports as soon as possible after completion of each required inspection.
(Res. 2010-8, passed 6-15-2010)