10-3-14: CONDITIONAL ACCEPTANCE:
   A.   Request: After all required improvements are complete, the subdivider shall, in writing, notify the city and the city engineer that the subdivision is complete and request conditional acceptance by the city. The conditional acceptance request shall be accompanied with:
      1.   A certificate, signed by the subdivider's engineer attesting to the fact that all improvements are installed, free from defects and that they comply with the intent of the construction standards. Any variation from said standards shall be noted in the certificate.
      2.   A Mylar copy of the as built construction drawings.
   B.   Inspection: The city engineer shall make an inspection within ten (10) days of receipt of the notice, and notify the subdivider in writing of any particulars in which this inspection reveals that the work is defective. The subdivider shall immediately make such corrections as are necessary to remedy such defects.
   C.   Notification Of Approval: The city engineer shall, as soon as the improvements are acceptable and after receipt of the as built drawings, notify the governing body, in writing, his approval of the improvements. The governing body shall, within fifteen (15) days after receipt of the city engineer's approval, present to the subdivider a notice of conditional acceptance establishing the date for beginning his two (2) year guarantee period. (Ord., 2-29-1996)