§ 52.16 APPLICATION.
   The control authority may notify an industrial user of its belief that the industrial user is, or may be, a significant user. Upon notification, the industrial user shall complete and submit an application for a wastewater discharge permit in the manner and form prescribed by the control authority. Failure of the control authority to so notify an industrial user shall not relieve any significant user of a duty to obtain a permit as required by this chapter.
   (A)   Existing industrial users shall submit a completed application on the form provided by the control authority within 60 days after being so directed and provided a form by the control authority.
   (B)   Proposed new industrial users shall request an application form and submit the completed application at least 90 days prior to start-up.
   (C)   An industrial user which becomes subject to a new or revised national categorical pretreatment standard and which has not previously submitted an application for a wastewater discharge permit as required by this chapter shall apply for a wastewater discharge permit within 90 days after the promulgation of the applicable national categorical pretreatment standard. The control authority may also initiate this action.
   (D)   A separate application shall be required for each separate location.
(‘83 Code, § 54.07) (Ord. 89-009, passed 8-21-89) Penalty, see § 52.99