3.14.245   Amendments necessitated by failure to meet construction deadlines.
   On February 3, 1981, City Council granted Teleprompter a one-hundred-twenty-day extension to account for construction delays experienced by Teleprompter. The extension is subject to the following conditions:
   A.    Where this franchise references a service rate which shall remain in effect with no increase for a period of three years, such time period for the service rate shall be extended for an additional one hundred twenty days.
   B.    Teleprompter will pay the City a three-hundred- thousand-dollar advance franchise fee. The franchise payment is to be nonrefundable and carries no restrictions by Teleprompter.
   C.    A one-hundred-twenty-day extension of time to complete the system is hereby granted and the penalty provisions contained in the franchise will apply should the one-hundred-twenty-day extension not be met. The amended completion dates for the five specified areas are as follows:
 
Area
Time
Previous Schedule
Amended Schedule
Area I
6 months
February 8, 1981
June 8, 1981
Area II
8 months
April 8, 1981
August 8, 1981
Area III
10 months
June 8, 1981
October 8, 1981
Area IV
14 months
October 8, 1981
January 8, 1982
Area V
18 months
February 8, 1982
February 8, 1982
 
(Ord. 2368 § 1, 1981).