15.47.025 Determining a Minor or Major Site Plan.
   A.   Notwithstanding any other provisions of this chapter, a Site Plan shall be considered Minor if:
   1.   The project qualifies for an exemption (Categorical or Statutory) from the requirements of CEQA; and
   2.   The project does not require a discretionary action (CUP, Variance, Minor Exception, etc.).
   B.   A Site Plan shall be considered Major if:
   1.   The Project does not qualify for an exemption (Categorical or Statutory) from the requirements of CEQA; and
   2.   The project requires a discretionary action (CUP, Variance, Minor Exception, etc.).
(Ord. 3232 (part), 2016; Ord. 2982, 2001).