§ 9-603 ACCURACY OF RECORDS.
   (a)   The developer, the developer's contractors, and the design engineer must ensure that all changes to the record drawings have been made by making adequate and proper entries on each page of the specifications, each sheet of engineering plans, and on any other documents where such notations are required to reflect the change properly.
   (b)   All changes to the record drawings shall be made in a manner that all information contained in the record drawings may be reasonably relied upon.
   (c)   In order to ensure the accuracy of records, all redline changes or entries should be made within 24 hours after the changes have occurred.
   (d)   The developer, the developer's contractors, and the design engineer must provide factual information regarding all aspects of the community facilities that were constructed to enable future modifications of the community facilities to be made without extensive site measurement, investigation, or examination.
(Ord. 23656-05-2019, § 1, passed 5-7-2019, eff. 6-1-2019)