The following items must be delivered to the city before a CFA can be closed out:
(a) An affidavit of bills paid and final lien waiver executed by the developer's contractors on forms provided by the city;
(b) Consent of surety forms for the payment and performance bonds executed by the surety company issuing the bonds; and
(c) Record drawings completed by the design engineer.
(Ord. 23656-05-2019, § 1, passed 5-7-2019, eff. 6-1-2019)