   The following items must be delivered to the city before a CFA can be closed out:
   (a)   An affidavit of bills paid and final lien waiver executed by the developer's contractors on forms provided by the city;
   (b)   Consent of surety forms for the payment and performance bonds executed by the surety company issuing the bonds; and
   (c)   Record drawings completed by the design engineer.