§ 9-501 WATER MISCELLANEOUS CONTRACTS.
   The water department's miscellaneous contract process is the city's in-house option for design and construction of water or wastewater infrastructure. The miscellaneous contract process is included in the city's installation policy and design criteria for water, wastewater and reclaimed water infrastructure. If public improvements are accepted by the city for the miscellaneous contract process, all required fees must be paid to the city before any plat holds related to a CFA may be released.
(Ord. 23656-05-2019, § 1, passed 5-7-2019, eff. 6-1-2019)
§§ 9-502—9-599 RESERVED.
ARTICLE VII: CONSTRUCTION, FINAL INSPECTION, AND CFA CLOSEOUT
§ 9-600 CONSTRUCTION NOTICE.
   For all construction activities in the right-of-way that impact traffic, the developer must provide notice to residences and businesses. The notice must be posted by the developer in the manner, form, and times proscribed by the city.
(Ord. 23656-05-2019, § 1, passed 5-7-2019, eff. 6-1-2019)
§ 9-601 FINAL INSPECTIONS.
   (a)   Except as otherwise provided in this chapter, a final inspection will not be scheduled until:
      (1)   The community facilities are fully constructed as determined by the construction inspector;
      (2)   All required material testing has been completed with a passing result and delivered to the construction inspector;
      (3)   Redline engineering sheets completed by the contractors showing differences between the engineering plans and the community facilities that have been constructed have been delivered to the construction inspector; and
      (4)   Compliance with the rules established by the transportation and public works department's construction office for obtaining a final inspection.
   (b)   Any deficiencies in or adjustments needed to the community facilities that are found by the construction inspector during a final inspection shall be listed on a punch list. Once all of the items on the punch list have been addressed and closed, a follow-up final inspection may be scheduled with the construction inspector.
   (c)   Once the construction passes final inspection, an acceptance letter is initiated by the construction inspector. The acceptance letter starts the closeout of the CFA and the process by which the city accepts and capitalizes the community facilities.
(Ord. 23656-05-2019, § 1, passed 5-7-2019, eff. 6-1-2019)