§ 9-318 REQUIREMENTS FOR A NOTICE TO PROCEED TO CONSTRUCTION.
   The following items are required before the city will issue a notice to proceed to construction for a CFA:
   (a)   A complete set of engineering plans accepted by the city;
   (b)   Proof of conveyance of all easements and temporary construction easements for the community facilities, and proof that all required permits have been issued;
   (c)   A CFA executed by the city and the developer;
   (d)   A financial guarantee acceptable to the city;
   (e)   Payment of all required fees;
   (f)   Complete contract document books that have been accepted by the city;
   (g)   A maintenance bond in the amount of the construction contracts executed in the name of the city covering community facilities to be constructed against defects in materials and workmanship for a period of two years after completion and acceptance of the community facilities by the city; and
   (h)   Payment and performance bonds provided by the contractors, or a development bond provided by the developer for a CFA that does not have city participation which eliminates the requirement that the contractors provide payment and performance bonds as specified in § 9-317.
(Ord. 23656-05-2019, § 1, passed 5-7-2019, eff. 6-1-2019)