Skip to code content (skip section selection)
Compare to:
§ 5.401 BATCH PLANT, ASPHALT OR CONCRETE (TEMPORARY).
   (a)   A temporary batch plant (concrete or asphalt) for road and highway construction may be located in any zoning district, provided that:
      (1)   The time period is no more than six months;
      (2)   The site is located 600 feet or more from properties upon which dwellings are constructed; and
      (3)   A site plan has been filed in the planning and development department, showing the location of the temporary batch plant, the distance from improved residential properties, and the streets to be paved.
   (b)   A temporary batch plant may be permitted for a period exceeding six months by special exception approved by the board of adjustment.
(Ord. 13896, passed 10-12-1999; Ord. 17522, § 5, passed 4-24-2007)