§ 52.22 SYSTEM DEVELOPMENT CHARGE.
   A system development charge (“SDC”) shall be assessed for all permanent connections to the Fort Wayne water system in accordance with the Fort Wayne Water Utility’s connection policies after filing of the tariff with the Indiana Utility Regulatory Commission, as follows:
Size of Meter
SDC
Size of Meter
SDC
5/8"
$580
3/4"
$870
1"
$1,450
1 ½"
$2,900
2"
$4,640
3"
$8,700
4"
$14,500
6"
$29,000
8"
$46,400
10"
$66,700
 
(Ord. G-14-18, passed 6-26-18; Am. Ord. G-11-19, passed 5-28-19)