(A) Street construction shall be of materials and in a manner according to specifications of the city’s Standard Specifications for Construction, as amended, as approved by the City Council.
(B) The developer shall complete streets within a subdivision in at least one-block increments and shall properly gravel and grade such streets prior to issuance of any building permit.
(C) The developer shall provide hard-surface paving within two years of completion of the lift of gravel, within the next construction season or following the sale of 30% of the lots in the subdivision, whichever first occurs, and the final paving lift within six months of the first lift. The city or its engineer shall inspect the first lift of paving and direct the developer to make any required corrections prior to completion of the final lift and shall inspect the final lift prior to street acceptance.
(Prior Code, § Q-12-1005)