903.06 SPECIFICATIONS AND GRADES.
   (a)   All sidewalks hereinafter constructed or reconstructed within the public right-of- way along any City street or highway shall be constructed or reconstructed according to material and construction specifications set forth in ODOT #608 Specifications.
   (b)   The concrete for the walks shall have a broomed finish, shall be sawed or impressed with joints at five foot intervals and the edges of all slabs shall be rounded to a one-half inch radius.
   (c)   The surface of all walks shall have a transverse slope of one-fourth to one-half inch per foot with the low side nearest to the curb line.
   (d)   Whenever a sidewalk is constructed or reconstructed to a grade that does not meet the grade of adjacent existing walks, the person constructing or reconstructing the sidewalk shall construct a ramp to eliminate any grade inequality. The material, workmanship and character of the ramp shall be determined by the Inspector.
   (e)   In the repairing of sidewalks no patching shall be allowed exceeding one square foot in area per slab.
(Ord. 97-2997. Passed 6-5-97.)