§ 1-20-6. GENERAL REQUIREMENTS.
   (A)   In planning and developing any subdivision or any development, the developer shall comply with the general principles set forth in this chapter for the provision of adequate facilities; and in every case the developer shall observe the procedure outlined in this chapter.
   (B)   A developer shall not avoid the intent of this chapter by submitting piecemeal applications for preliminary plats or site plans. However a developer may seek approval of only a portion of the subdivision or development, provided that the impact from all previously approved preliminaries or site plans from that development shall be considered during the APF review of each subsequent portion of the development.
   (C)   Except as provided in § 1-20-7, all parcels must receive APFO approval prior to site plan subdivision, or Phase II approval.
(Ord. 98-03-205, 3-17-1998; Ord. 09-20-524, 7-7-2009; Ord. 14-23-678, 11-13-2014)