§ 153.08 PREPARATION FOR INSPECTION; CONCEALED WORK.
   (A)   The electrical contractor or electrician installing electrical wiring for which inspection is required shall notify the Electrical Inspector when the project is ready for inspection.
   (B)   No electrical contractor or electrician or individual shall conceal electrical wiring or other electrical apparatus which is required to be inspected until after it has been inspected and approved. Concealed work which will not permit full inspection shall not be accepted.
   (C)   All electrical work shall be finished and ready for service before final inspection.
(Ord. 950.3-9-2002, passed 10-14-2002)