§ 155.169 REPORTS AND SITE DEVELOPMENT AND OPERATIONAL PLANS.
   (A)   Detailed plans, specifications, maps and reports shall be submitted in triplicate to the Planning Commission for review. The data in the following reports should be prepared in a form, which facilitates its use in proper engineering design of the landfill. Problem areas must be delineated and recommendations for proper solution included in the report. The plans, specifications and maps for the operational plan may be submitted in the manner required by the permitting regulations of the Division of Waste Management of the Natural Resources and Environmental Protection Cabinet for solid waste landfills contained in 401 KAR 47:170.
   (B)   Operation plan and maps must be prepared including the following information:
      (1)   The proposed fill area;
      (2)   Any borrow area;
      (3)   Access roads;
      (4)   On-site drives;
      (5)   Grades for proper drainage of each lift required and a typical cross-section of a lift;
      (6)   Special drainage devices, if necessary;
      (7)   Location and type of fencing;
      (8)   Structures existing or to be located on the site;
      (9)   Existing wooded areas, trees, ponds or other natural features to be preserved;
      (10)   Existing and proposed utilities;
      (11)   Phasing of landfill operations on the site;
      (12)   A plan and schedule for site restoration and completion;
      (13)   A plan for the ultimate land use of the site if possible;
      (14)   Method of operation including weighing of wastes, cross-sectioning the site at definite time intervals, thickness of cover material, depth of cells and lifts, compaction, wet weather procedures, cold weather procedures, amount, type and size of equipment and personnel; and
      (15)   And all other pertinent information to indicate clearly the orderly development operation and completion of the landfill.
(Ord. 8, passed 10-23-1987, § 4.605; Ord. 3-2002, passed 5-3-2002)