§ 52.12 EFFECT OF PERMIT.
   (A)   Authority granted; no property right or other interest created. A permit from the village only authorizes a permittee to undertake certain activities in accordance with this chapter on village rights-of-way and does not create a property right or grant authority to the permittee to impinge upon the rights of others who may have an interest in the public rights-of-way.
   (B)   Duration. No permit issued under this chapter shall be valid for a period longer than 180 days unless construction is actually begun within that period and is thereafter diligently pursued to completion.
   (C)   Pre-construction meeting required. No construction shall begin pursuant to a permit issued under this chapter prior to attendance at a pre-construction meeting by the permittee and all major contractors and subcontractors who will perform any work under the permit. The pre-construction meeting shall be held at a date, time and place designated by the village, with such village representatives in attendance as the village deems necessary. The meeting shall be for the purpose of reviewing the work under the permit and reviewing special considerations necessary in the areas where work will occur, including without limitation the presence of other utility facilities in the area and their locations, procedures to avoid disruption of other utilities, use of rights-of-way by the public during construction and access and egress by adjacent property owners.
   (D)   Compliance with all laws required. The issuance of a permit by the village does not excuse the permittee from complying with other requirements of the village and all applicable statutes, laws, ordinances, rules and regulations.
(Ord. 2479, passed 6-16-08)