§ 152.20 PERMITS.
   (A)   Permit/approval. See § 152.18(A).
   (B)   Action on application. The Building Official shall examine or cause to be examined all applications for permits and amendments thereto within a reasonable time after filing, and in accordance with the requirements of the OBC or RCO as applicable.
   (C)   Permit valuation. The Building Official shall attach his signature or stamp to every permit (Certificate of Plans Approval) or he may authorize an appropriately certified backup Building Department employee or third party contractor to affix such stamp thereto to validate the permit.
   (D)   Posting of permit. A true copy of the building permit or such other instrument serving the purpose as the Building Official may authorize or approve shall be posted on the site of operations open to public inspection during the entire time of prosecution of the work and until the completion of same.
(Ord. 24-2019, passed 8-5-19)