§ 51.20 INSPECTIONS.
   (A)    An approved plan bearing the City Engineer's stamp of approval shall be maintained at the site, along with any required permit, during the progress of the work.
   (B)   Inspection and notification procedures and time allowed to correct deficiencies shall be as established by the City Engineer.
   (C)    The Inspector shall inspect the work covered by the plan and permit. At any stage of construction when conditions are not as stated or shown on the plan, the Director, with the approval of the City Manager, may order further work stopped until approval is obtained for a revised plan conforming to existing conditions.
   (D)    If at any stage of the work the Inspector determines that the conditions are such that further work as authorized by the existing permit is likely to imperil any person, property, public way, watercourse, or drainage structure, the Inspector may require, as a condition to allowing the work to proceed, that such reasonable safety precautions be taken as considered available to avoid the likelihood of such peril. Where it appears that storm damage may result because the grading is not complete, the Director, with the approval of the City Manager, may order work to be stopped and the developer required to install temporary planting to control erosion, install temporary structures or take such other measures as may be required to protect adjoining property or the public safety.
   (E)   Where no permit has been required and it is evident that construction and grading has caused the existing surface drainage in the general area to be impaired, created an erosion hazard or become a source of sediment to any adjacent land or watercourse, the Director shall:
      (1)   Have the Developer verbally notified to take measures necessary to correct the situation within a specific length of time, or
      (2)   Take immediate action, if necessary to protect persons or property from damage - by causing corrective measures to be taken and charging the Developer for all coast incurred by the city as a result of such action;
      (3)   Have the corrective measures performed by other that the developer, with the incurred expense charged to the developer, if not completed by the developer within the specified time period;
      (4)   recommended to the City Manager that the Building Department withhold the issuance of a certificate of occupancy for all structures on the project area until all costs incurred by the city have been paid in full the by developer.
(Ord. 04-1990, passed 3-5-90) Penalty, see § 51.99