§ 150.217 BASIC DESIGN REQUIREMENTS.
   (A)   As a prerequisite of preliminary plat review by the Planning Department, the developer shall have informed all utilities which will be impacted or have an interest in the proposed subdivision of the tentative plans and learned the general requirements for sewage disposal, water supply, electric transmission, grading and drainage as applied to the project location.
   (B)   It shall be the responsibility of the developer to provide with preliminary plat submittal, letters of intent to serve by all utility companies serving the town and/or project area.
   (C)   In addition, approval of every preliminary and final plat by the Council is conditional upon compliance by the developer with:
      (1)   Rules as may be established by the State Department of Transportation relating to provisions for the safety of entrance upon and departure from abutting state primary highways;
      (2)   Rules as may be established by a county flood control district relating to the construction or prevention of construction of streets in land established as being subject to periodic inundation;
      (3)   Rules as may be established by the State Department of Environmental Quality and the State Department of water resources relating to the provision of domestic water supply and sanitary sewage disposal; and
      (4)   Obtaining a certificate of assured water supply from the Director of Water Resources unless the subdivision is located within an area designated as having an assured water supply by the Director of Water Resources pursuant to A.R.S. § 45-576(A), (B) and (E). It shall be noted on the face of the preliminary plat that a certificate of assured water supply has been submitted with the plat or that the proposed subdivision is within an area designated as having as assured water supply, pursuant to A.R.S. § 45-576(A), (B), (E) and (I).
(Prior Code, Ch. 4, Art. V, § 4-393) (Ord. 432-06, passed 6-19-2006)