Within five working days of the pre-application meeting and based on the recommendation of the Committee, the Planning Director may issue the appropriate notice to proceed according to one of the following procedures:
(A) Subdivision. If the sketch plat involves a subdivision only, the Planning Director will issue a written notice advising the developer to proceed with the preparation of a preliminary plat to be considered by the Planning Commission and the Town Council.
(B) Planned unit development (PUD). The Site Plan Review Committee may determine that a PUD is required if any of the following applies:
(1) The tract is sufficiently large to comprise an entire neighborhood;
(2) If the tract is to be developed in multiple phases; and
(3) The tract initially proposed for platting is only a portion of a larger land area, the development of which is complicated by unusual topographic, utility, land use, land ownership or other conditions.
(Prior Code, Ch. 4, Art. V, § 4-369) (Ord. 432-06, passed 6-19-2006)