(A) All work and materials shall conform to the Maricopa Association of Governments Details, Specifications and Standards approved by the town (hereinafter referred to as M.A.G. Specifications), and revisions as to these standard specifications apply to trench backfill material, backfill compaction and roadway surface restoration except as noted in these special provisions. In case of conflict between M.A.G. Specifications and these provisions, the provisions herein shall apply.
(B) Other agency specifications for construction material which are equal to M.A.G. Specifications, listed herein, may be substituted as satisfactory alternatives with prior written approval of the Director of Public Works.
(C) Other construction methods, which are determined from engineering studies and laboratory tests, may be substituted as satisfactory alternatives with prior written approval of the Director of Public Works.
(Prior Code, Ch. 16, Art. II, § 16-33) (Ord. 55, passed 12-15-1983)