1113.38 LAPSE OF APPROVAL.
   If no work progresses on an approved application within one (1) year from the date of Administrative or Planning Commission approval, the approval shall lapse and become null and void. Issuance of permits and posting of construction bonds when required shall constitute work. The approval shall lapse if the permit expires prior to commencing the work.
   Example: The maximum time period to complete a project is two (2) years. This is assuming the applicant waits until the 365th day after approval to obtain a permit. Permits are valid for one (1) year. No additional permits will be issued regardless of a project’s start date or completion status.
(Ord. 2023-115. Passed 12-19-23.)