Section 9.1.50. Approval of Building Permit Procedure.
   A.   Submit building permit application to Fairfield Town. (www.fairfieldtown.org/);
   B.   The Building Department will check that all plans, deeds ,dedications and any other required documents needed have been submitted and approved and that the Planning Commission has approved the site plan.
   C.   Pay estimated building fees to Fairfield Town.
   D.   The Building Department will submit plans and documents to a contracted engineer for plan review and inspections.
   E.   Once plans have been approved, Fairfield Town will evaluate if any other building permit fees need to be paid at this time.
   F.   The Building Department will issue a building permit along with name and numbers for inspections.
   G.   Once all inspections are completed by the contracted engineer the building department will do a final review and inspection.
   H.   Once final review and inspection is completed and any remaining fees are paid then an occupancy permit will be issued.
   I.   The Building Department may revoke at any time a permit which has been issued for any building constructed or being constructed or which would be or result, if constructed, in a violation of the Building Code or any Ordinance of this municipality.
   J.   Documents Required:
      1.   Stamped digital building plans;
      2.   Proof of Fairfield acceptable culinary water transfer or well permit. State approved culinary water transfer and point of diversion change, or well permit acceptable to the Town of Fairfield;
      3.   Septic system plan approved and signed by Utah County;
      4.   Signed approval from Cedar Valley Fire Department ;
      5.   Contractors Hold Harmless Agreement;
      6.   Arsenic report;
      7.   Any other documents required by the Planning Commission, Building Heads, Fire Department, or Town Council pertinent to the proposed development or building; and
      8.   Site Plan signed and approved by the Planning Department.
Rev. ord. 03142023-1, passed 03-14-2023.