§ 53.088 REQUIREMENTS FOR CONNECTION.
   A qualifying facility, before being connected to the municipal electric utility shall meet the following provisions and requirements:
   (A)   Provide an expected service date to the municipal electric utility;
   (B)   Provide a complete description of the proposed generating facility, including its location, source of fuel, nameplate data of principal components and drawings and exhibits that describe the size, character and continuity of service and the location of the generating facility;
   (C)   Provide the character of service of the generating facility including the proposed electrical current, frequency (Hertz), voltage, number of phases, size of all electrical wire to be used in the generating facility installation;
   (D)   Provide the equipment and facilities to meet the requirements for metering and protective controls as described in this subchapter; and
   (E)   Provide certification of compliance with all other legal requirements of the generating facility installation and the emissions therefrom.
(1986 Code, § 8.10.040) (Ord. 1197, passed 3-9-1982)