§ 55.059 BUILDING SEWER; PLACEMENT.
   (A)   Whenever possible, the building sewer shall be brought to the building at an elevation below the basement floor. No building sewer shall be laid parallel to any bearing wall if within three feet of any wall, which might thereby be weakened. The depth shall be sufficient to afford protection from frost. The building sewer shall be laid at uniform grade and in straight alignment insofar as possible. Changes in direction or grade shall be allowed only when a proper manhole is constructed at the location of the change.
   (B)   In all buildings in which any building drain is too low to permit gravity flow to the public sewer, sanitary sewage carried by the drain shall be lifted by approved artificial means and discharged to the building sewer.
(1986 Code, § 7.28.090) (Ord. 1240, passed - -1984)