1109.02   CONSTRUCTION PLANS.
   Construction plans shall contain the following:
(a)   A detailed plan and profile of all existing and proposed facilities at a horizontal scale of one inch equals fifty feet or less and a vertical scale of one inch equals ten feet or less.
(b)   The locations shall be shown of existing facilities, existing structures, drives, and other facilities which may be affected by the improvements.
(c)   All proposed lots and streets shall be delineated in plan, showing radii, function of curves, curbs, sidewalks, steps and any other relevant information.
(d)   Street names, lot numbers, lot dimensions and easements shall be shown.
(e)   The plans and profiles of proposed streets, sanitary sewers, storm sewers, and water mains, with grades and sizes indicated. Water lines, gas lines, and sanitary sewer details shall be shown as required by the authority having jurisdiction. Other details shall be shown as required by the Planning Director or County Board of Health. Plan for the detention/retention of storm water shall be provided in accordance with Chapter 1117.
(f)   Where a street ends at a property line or may be extended in the future, the profile shall be shown for at least 200 feet beyond the subdivision property line or end of a street.
(g)   A plan of any proposed gas distribution system showing pipe sizes, location of valves and other facilities.
(h)   Notes.
(1)   General notes and miscellaneous details shall include any pertinent notes and details that are not covered in the standard drawings or the plan or profile.
(2)   Construction notes as necessary.
(3)   Each set of plans must include the statement that "roof drains, foundation drains, and other clear water connections to the sanitary sewer are prohibited."
(4)   A note shall be included as follows: "All work shall be done under the supervision of the Public Works Director and Public Utilities Director and in accordance with the City of Fairfield Subdivision Regulations.
(Ord. 167-95. Passed 11-13-95.)