(A) Public projects of $60,000 or less may be performed by the employees of the town by force account or by negotiated contract or purchase order awarded by the Town Manager. The approval of contracts by the Town Manager is subject to the town's administrative purchasing policies adopted by Council Resolution 13-30.
(B) Public projects of $200,000 or less may be let to contract by informal procedures as set forth in this chapter.
(C) Public projects of more than $200,000 shall, except as otherwise provided in the Uniform Public Construction Cost Accounting Act, be let to contract by formal bidding procedures.
(Prior Code, § 3.36.020) (Ord. 644, passed - -1995; Am. Ord. 795, passed 10-7-2015; Am. Ord. 823, passed 11-7-2018)