Within 15 working days after receipt of an application for an approval under this Code the Building, Planning & Zoning Manager shall determine whether the application is complete. If the Building, Planning & Zoning Manager determines that the application is complete, he shall notify the applicant in writing that the application has been accepted for filing. If the Building, Planning & Zoning Manager determined that the application is not complete, he shall notify the applicant in writing, specifying the deficiencies of the application, including any additional information which must be supplied, and that no further action need be taken by the Village on the application until the deficiencies are corrected.
(a) Remedy of Deficiencies. If the applicant fails to correct the specified deficiencies within 90 days of the notification of deficiency, the Village may deem the application withdrawn.
(b) Effect of Determination. Any time limits for completion of a review of an application and the rendering of a final decision, where provided for in this Chapter 1276, shall commence as of the date that the Building, Planning & Zoning Manager determined that the application is complete.
(Ord. 12-64. Passed 3-12-13; Ord. 20-24. Passed 3-10-20.)