10-1-3-4: SEWER MAIN EXTENSION/ENLARGEMENT:
Sewer main facilities may be extended by subdivider, developer, property owner, or other persons in accordance with plans and specifications submitted to, and approved by, the city engineer.
   A.   Minimum Size; Cost: The inside diameter of every sewer main shall not be less than eight inches (8"), except as may be determined by the city engineer. The subdivider, developer, property owner, or other person shall construct all sewer mains in accordance with the plans and specifications as submitted to, and approved by, the city engineer; and pay any and all costs for the minimum size sewer main required for this development as determined by the city engineer.
   B.   Dedication: Upon connection to the sewer system, the subdivider, developer, property owner, or other person shall dedicate all new sewer mains that connect into the existing city sewer system to the city. Upon dedication and after the one year contractor warranty period has expired, the city will operate and maintain the new sewer mains.
   C.   Construction Of Larger Mains: Whenever, in the opinion of the city council or city engineer, it is necessary that a sewer main be constructed of a capacity larger than the minimum capacity set forth in subsection A of this section, the subdivider, developer, property owner, or other person shall be required to purchase materials, construct and install such oversized sewer main as required. (Ord. 453, 11-29-1990)