(A) Apart from any project or building plans required to be submitted to the city, a detailed site plan, drawn to scale, shall be filed with the Zoning Administrator, as part of any application for a building permit for a permitted use.
(B) The site plan shall show where pertinent:
(1) Scale and north arrow;
(2) Lot lines and their dimensions. Public or main buildings, or dwellings of any type require permanent reference monuments in each of the four corners of the lot it is to be built on. If a lot contains more than four corners, only four permanent reference monuments are required. If a lot contains less than four corners at least three permanent reference monuments are required. All monuments shall be properly set in the ground and approved by a Registered Land Surveyor (licensed in the state) prior to approval of the building permit application. If permanent reference monuments are already in place additional monuments are not required;
(3) Adjacent streets, roads, rights-of-way, ditches, easements, and land uses;
(4) Location of all existing structures on subject property and adjoining properties (completely dimensioned, including utility lines, poles, fences, and the like);
(5) Existing utility line locations and sizes;
(6) Existing and proposed grading, drainage, and landscaping plans;
(7) Location of proposed construction and improvements, including location of proposed sewer connection, all landscape elements, retaining walls, drainage works, and signs;
(8) Motor vehicle access, including individual parking stalls, circulation patterns, curb, gutter, and sidewalk and trail location;
(9) Trash storage plans;
(10) Necessary explanatory notes;
(11) Name, address, and telephone number of builder and owner; and/or
(12) Other information which may be requested by the Zoning Administrator, city staff or in this chapter.
Penalty, see § 155.999