§ 155.014 CERTIFICATE OF OCCUPANCY REQUIRED.
   No land shall be used or occupied and no building hereafter structurally altered or erected, shall be used or changed in use until a certificate of occupancy shall have been issued by the city staff stating that the building or structure or the proposed use thereof, or the use of land, complies with the provisions of this zoning code. A like certificate shall be issued for the purpose of maintaining, renewing, changing, or extending a nonconforming use. A certificate of occupancy either for the whole or a part of a building or structure shall be applied for coincidentally with the application for a building permit, and shall be issued within ten days after the erection or structural alteration of such building or structure, or part thereof, shall have been completed in conformity with the provisions of this chapter.
(Ord. 2008-001, passed - -2008) Penalty, see § 155.999