§ 152.41 PHOTOVOLTAIC SOLAR ENERGY SYSTEMS.
   The following standards shall apply to photovoltaic solar energy systems.
   (A)   No grid-intertie photovoltaic solar energy system shall be installed until documentation has been given to the Zoning Administrator that the owner has notified the utility company of the customer’s intent to install an interconnected customer-owned generator. Documentation may consist of an interconnection agreement or a written explanation from the utility provider or contractor outlining why an interconnection agreement is not necessary. Off-grid systems are exempt from this requirement.
   (B)   Photovoltaic solar energy system components must have an Underwriters Laboratory (UL) listing and solar hot water systems must have a Solar Rating and Certification Corporation (SRCC) rating.
(Ord. 2017-002, passed 6-13-2017) Penalty, see § 152.99