§ 51.111 SPECIFIC INDUSTRIAL USER REQUIREMENTS.
   (A)   In addition to all other requirements, each industrial user who discharges an industrial discharge into the POTW shall also:
       (1)   Obtain an industrial discharge permit from the Sewer Department. Any application for a permit or an amended permit shall contain the information specified in the application form or such other information as may be requested by the Sewer Department. After the effective date of this subchapter, any person intending to commence any new industrial discharge(s) or any additional industrial discharge(s) not already allowed pursuant to an existing permit shall first obtain a new or an amended industrial discharge permit, as applicable, from the Sewer Department prior to initiating the discharge(s);
      (2)   Comply fully with all requirements and conditions of any industrial user permit. Once a permit is issued, no industrial user shall:
         (a)   Make any new or increased industrial discharge; or
         (b)   Otherwise make any change in the nature of its industrial discharge(s) if the change will cause any new or increased industrial discharge.
      (3)   Provide all of the pretreatment necessary to comply with the categorical standards and pretreatment requirements imposed by this subchapter;
      (4)   Maintain a continuous discharge record which clearly identifies the:
         (a)   Dates and times of all industrial discharges; and
         (b)   Nature, concentration(s), and volume(s) of all the discharges.
      (5)   Provide the Sewer Department with all the same self-monitoring reports and notices which the industrial user is required to submit to any other authority in accordance with the provisions of 40 C.F.R. § 403.12. In particular, the industrial user shall meet the requirements of:
         (a)   Notices which must be filled within 180 days of the adoption of any categorical standard, including a compliance schedule;
         (b)   Notices which must be filed within 90 days of any final compliance date;
         (c)   Reports which must be filed by the industrial user in June and December of each year;
         (d)   The immediate notice which must be given after a slug load release of any industrial discharge;
         (e)   The sampling and analysis of pollutants discharged to the POTW; and
         (f)   The maintenance of records by the industrial user.
   (B)   An industrial user with an industrial discharge permit issued prior to the effective date of this subchapter shall file with the Sewer Department within 90 days of the effective date of this subchapter a written statement by an authorized agent of the permittee certifying that the permittee is in compliance with the terms of this subchapter.
   (C)   If an industrial user with an industrial discharge permit cannot provide the certification set forth in division (B), then the industrial user shall submit an application for a new industrial permit which shall include a proposed schedule for coming into compliance with the terms of this subchapter.