(A) Where it is in the interest of the petitioner to complete construction of the improvements required by the primary approval in phases rather than at once, the petitioner shall so state in writing to the Plan Commission, and deliver the request, together with maps and drawings showing the intended phasing of the project.
(B) The Plan Commission may, at its option, provide secondary approval to each phase as it is built, provided that at no time shall the phasing plan produce an unsafe condition or utility layout that is not in compliance with the requirements of Indiana law or this code.
(Ord. 03-27, 855-20, passed 12-22-2003)