The secondary plat and confirmation of construction plans and confirmation of storm water pollution prevention plans shall include the information required on the checklist for application for secondary approval set forth in the Elkhart County Advisory Plan Commission Rules of Procedure and evidence of compliance with all conditions of primary approval and the following information.
(A) Scale and page size. The secondary plat shall be drawn at a standard engineering scale of not more than 100 feet to one inch. The maximum page size shall not exceed 18 inches by 24 inches. A digital copy shall also be provided of the secondary plat, in a format specified by the Department. In lieu of a digital copy of the secondary plat, the applicant may pay a fee as adopted in the Plan Commission’s Rules of Procedure to cover the cost of digitizing.
(B) Area for public uses. The overall area to be allocated for park, school, recreational and other public and semipublic sites.
(C) Storm water. Storm water pollution prevention plan (SWPPP) meets the standards of 327 I.A.C. 15-5 (Rule 5). Soil may not be moved until a plan has been approved;
(D) Phasing schedule. The schedule of any phasing of the project;
(E) Significant conditions. Other significant conditions of the area proposed to be improved;
(F) Wetland mitigation plan. An appropriate written certification of the wetland mitigation plan and the approved permit by the appropriate state or local agency for any development where wetlands will be adversely affected; and
(G) Drainage maintenance certificate. The secondary plat shall include a drainage maintenance certificate as provided in the Elkhart County Advisory Plan Commission Rules of Procedure.
(Ord. 2009-67, passed 3-2-2009; Ord. PC 2016-20, passed 7-18-2016)