§ 52.27 COMPLIANCE SCHEDULES.
   (A)   Any user, which is not in compliance with any limitations or requirements of this chapter, shall develop a compliance schedule of corrective measures to be taken in order to return to compliance. This schedule shall be submitted to the Director for review and approval. If the user does not submit an acceptable schedule, the Director may develop and enforce a schedule for the user. This schedule shall contain milestone dates for the commencement and completion of major events leading to the construction and operation of additional facilities required for the user to comply with this chapter. This may include, but is not limited to, dates relating to:
      (1)   Hiring an engineer;
      (2)   Hiring other appropriate personnel;
      (3)   Completing preliminary plans;
      (4)   Completing final plans and specifications;
      (5)   Executing contracts for major components;
      (6)   Commencing construction;
      (7)   Completing construction and startup; and
      (8)   All other acts necessary to achieve compliance with this chapter.
   (B)   Any user subject to a compliance schedule shall submit a progress report to the Director no later than 14 calendar days following each date in the compliance schedule. This report shall include whether the user complied with the increment of progress to be met on that date, the reason for any delay, if the date was not met, and the steps being taken to return to compliance. In no event, can more than 9 months elapse between progress reports.
(Ord. 5746, passed 7-1-2019)