(A) The contractor shall maintain suitable means of access for property owners abutting the streets and highways involved in construction except as specifically permitted otherwise by the owner. SUITABLE ACCESS shall mean a roadway of sufficient width free from ruts, potholes and mud holes and capable of carrying a passenger car without damage to the car. When access must be denied due to construction, the contractor shall provide suitable access within 24 hours after responsible construction is completed.
(B) Whenever construction is stopped due to inclement weather, weekends, holidays or other reasons, suitable access shall be provided for all property owners.