§ 102.60 CONSTRUCTION DOCUMENTS.
   Plans for fire alarms systems, water-based fire protection systems, fire pumps, special hazard fire suppression systems, high-piled storage arrangements and firestop systems shall be submitted for review. Each applicable submittal must contain the following information:
   (A)   Sprinkler/standpipe systems.
      (1)   One full set of sprinkler/standpipe plans.
      (2)   One full set of sprinkler/standpipe calculations.
      (3)   One copy of the sprinkler construction design release (CDR).
      (4)   One set of manufacturer's cut-sheets for all sprinkler heads in the design.
   (B)   Fire alarm systems.
      (1)   One full set of fire alarm plans.
      (2)   One set of battery calculations.
      (3)   One copy of the fire alarm construction design release (CDR).
      (4)   One set of manufacturer's cut-sheets for the Fire Alarm
Control Panel (FACP) and fire alarm components.
      (5)   One fire alarm sequence of operation matrix.
   (C)   Special hazard fire protection systems.
      (1)   One set of plans (if applicable).
      (2)   One set of engineering data (if applicable).
      (3)   One copy of the construction design release (if applicable).
      (4)   One set of manufacturer's cut-sheets for system components.
   (D)   Fire pumps.
      (1)   One copy of the manufacturer's fire pump specifications.
      (2)   One copy of the manufacturer's certified pump test characteristic curve.
   (E)   Firestop systems.
      (1)   Through-penetration firestop systems.
      (2)   Membrane-penetration firestop systems.
      (3)   Fire-resistant joint systems.
      (4)   Perimeter fire barrier systems.
      (5)   Fire-rated duct and air-transfer openings.
(Ord. 2023-17, passed 11-13-23)