§ 53.100 CONCEPTUAL DRAINAGE PLAN REVIEW.
   (A)   In order to gain an understanding of the drainage requirements for a specific project, a project owner or developer shall submit conceptual drainage plans and calculations for review by the DSM and/or the permitting officer. A meeting to review the conceptual SWPPP will then be scheduled
   (B)   The direction provided by the DSM and/or the permitting officer during such a review is based on preliminary data and shall not be construed as a preliminary determination, final drainage approval, or binding on either party.
   (C)   The following is a general listing of minimum data requirements for the review of conceptual drainage plans:
      (1)   Two complete sets of conceptual plans showing general project layout, including existing and proposed drainage systems (plan sheets must be at least 11 inches by 17 inches).
      (2)   General description of the existing and proposed drainage systems in a narrative form.
      (3)   Watershed boundaries with United States Geologic Survey (USGS) contours or best information possible.
(Ord. 2023-22, passed 12-28-23)