(A) Design plans, technical information, and the SWPPP with post-construction storm water quality measures shall be submitted per the application process in § 53.075 et seq. The post-construction section of the SWPPP shall include the requirements identified in the Standards.
(B) It will be the responsibility of the project site owner to ensure proper construction and installation of all storm water BMPs in compliance with this chapter, the Standards, the terms and conditions of the approved storm water management permit, and CSGP.
(Ord. 2023-22, passed 12-28-23)