§ 53.079 INSPECTION, MAINTENANCE, RECORD KEEPING, AND REPORTING.
   (A)   Following approval of the SWPPP by the DSM and commencement of construction activities, the DSM and/or the permitting officer has the authority to conduct inspections of the site to ensure full compliance with this chapter, the Standards, the terms and conditions of the approved storm water management permit, and CSGP.
   (B)   A self-monitoring program shall be implemented by the project site owner to ensure the SWPPP is working effectively in accordance with the CSGP. At a minimum, the self-monitoring program shall meet the requirements in the Standards.
   (C)   Following the final completion of construction and the receipt of as-built drawings, the DSM and/or the permitting officer has the authority to inspect new development and redevelopment sites to verify that all on-site storm water conveyances and connections to the storm drainage system are in compliance with this chapter.
   (D)   Although self-monitoring reports do not need to be submitted to DSM and/or the permitting officer, the DSM and/or the permitting officer has the right to request complete records of maintenance and monitoring activities involving storm water pollution prevention measures. All evaluation reports for the project site must be made available to DSM and/or the permitting officer, in an organized fashion, within 48 hours upon request.
(Ord. 2023-22, passed 12-28-23)