(a) Improvements To Be Extended To Farthest Limit of Parcel or Lot. Any and all improvements or utility services required by this Article for the Subdivision, Certified Survey Map, or Condominium shall be extended to the farthest limit of the parcel or lot upon which a building permit is requested unless the owner is excused from meeting such requirement by the Village Board.
(b) Financial Sureties for Extension of Improvements Required. In the event the improvements are required to the end of the parcel or lot, the Subdivider or Condominium Developer (as applicable) shall be required to post financial sureties with the Village pursuant to Section 14-1-51 if improvements are not made.
(c) Extra-Sized and Off-Site Facilities. When any public improvements of adequate capacity are not available at the boundary of a proposed land division, the Village, or its duly authorized representative, shall require, as a prerequisite to approval of a Final Plat, Certified Survey Map or Condominium Plat, assurances that such improvement extensions shall be provided as follows in accordance with the following standards:
(1) Design Capacity.
All improvements within or entering or leaving the proposed development shall be installed to satisfy the service requirements for the entire service or drainage area in which the development is located and the improvements shall be of sufficient capacity to handle the expected development of the overall service area involved.
(2) Extra-sized and Off-size Improvements.
Where improvements of adequate size needed to serve the development are not available at the boundary of the development, the subdivider shall proceed under one (1) of the alternatives as identified in Section 14-1-50(a).
(3) Lift Stations.
Where sanitary or storm sewer lift stations and force mains are required to lift sewage to the gravity system, the Subdivision, Condominium or Certified Survey Map Developer (as applicable) shall have plans, profiles, specifications and estimated operation and maintenance costs prepared for the installation of such facilities to the Village Engineer's requirements. Equipment similar to existing Village equipment shall be utilized whenever possible. The installation, inspection, supervision and engineering fees for lift stations and/or force mains shall be paid for by the Subdivider/Developer unless otherwise determined and agreed upon by the Village Board. Gravity sanitary sewer service shall be employed whenever determined by the Village Engineer to be feasibly accessible.