(a) Engineering Reports, Construction Plans and Specifications. As required by Section 14-1-31, general engineering reports, plans and proposed specifications shall be submitted simultaneously with the filing of the Preliminary Plat. At the Final Plat stage, detailed construction plans for the required improvements conforming in all respects with the standards of the Village Engineer and the ordinances of the Village shall be prepared at the Subdivision, Condominium or Certified Survey Map Developer (as applicable)'s expense by a professional engineer who is registered in the State of Wisconsin, and said plans shall contain his/her seal. Such plans, together with the quantities of construction items, shall be submitted to the Village Board or Village Engineer for their approval and for their estimate of the total cost of the required improvements; upon approval they shall become a part of the contract required. Simultaneously with the filing of the Final Plat with the Village Administrator, or as soon thereafter as practicable, copies of the construction plans and specifications, where applicable, shall be furnished for the following public improvements:
(1) Street Plans and Profiles showing existing and proposed grades, elevations and cross sections of required improvements.
(2) Sanitary Sewer plans and profiles showing the locations, grades, sizes, elevations and materials of required facilities.
(3) Water Main plans and profiles showing the locations, sizes, elevations and materials of required facilities.
(4) Storm Water and Open Channel plans and profiles showing the locations, grades, sizes, cross sections, elevations and materials of required facilities.
(5) Erosion and Sedimentation Control plans showing those structures required to retard the rate of runoff water and those grading and excavating practices that will prevent erosion and sedimentation. Such plans shall comply with the Village's Construction Site Erosion Control Code and Post-Construction Stormwater Management Code (Title 15, Chapters 2 and 3).
(6) Landscaping Plans showing the locations, age, caliper, species and time of planting of any required grasses, vines, shrubs and trees meeting the requirements of Section 14-1-45.
(7) Master Site Grading Plans showing existing and proposed lot corner elevations, top of curb elevations, building location and proposed first floor building elevation, and shall show control and direction of drainage for each lot within the subdivision and for drainage adjacent to the plat.
(8) Additional special plans or information as required by Village officials.
(b) Action by the Village Engineer. The Village Engineer shall review or cause to be reviewed the plans and specifications for conformance with the requirements of this Chapter and other pertinent Village ordinances and design standards recommended by the Village Engineer and approved by the Village Board. If the Village Engineer rejects the plans and specifications, he/she shall notify the owner, who shall modify the plans or specifications or both accordingly. When the plans and specifications are corrected, the Village Engineer shall approve the plans and specifications for transmittal to the Village Board. The Village Board shall approve the plans and specifications before the improvements are installed and construction commenced.
(c) Construction and Inspection.
(1) Construction Authorization; Building Permits; Lien Waivers.
Prior to starting any of the work covered by the plans approved above, written authorization to start the work shall be obtained from the Village upon receipt of all necessary permits and in accordance with the construction methods of this Chapter. Building permits shall not be issued until all improvements required by this Chapter are satisfactorily completed, and the Subdivider/Developer has furnished lien waivers for all contractors..
(2) Completion Schedule.
Construction of all improvements required by this Chapter shall be completed within two (2) years from the date of approval of the Preliminary Plat by the Village Board, unless good cause can be shown for the Village Board to grant an extension unless another time frame is set forth in the Developer's Agreement for phased developments as approved by the Village Board.
(3) Inspections.
During the course of construction, the Village Engineer shall make such inspections as the Village Board deems necessary to ensure compliance with the plans and specifications as approved. The owner shall pay the actual cost incurred by the Village for such inspections. This fee shall be the actual cost to the Village of inspectors, engineers and other parties necessary to ensure satisfactory work.
(d) Subdivider to Reimburse the Village for Costs Sustained. The Subdivider/Developer of land divisions within the Village shall reimburse the Village for its actual cost of design, inspection, testing, construction and associated legal and real estate fees for the required public improvements for the land division. The Village's costs shall be determined as follows:
(1) The cost of Village employees' time engaged in any way with the required public improvements based on the hourly rate paid to the employee multiplied by a factor determined by the Village Administrator to represent the Village's cost for expenses, benefits, insurance, sick leave, holidays, vacation and similar benefits.
(2) The cost of Village equipment employed.
(3) The cost of mileage reimbursed to Village employees which is attributed to the land division.
(4) The actual costs of Village materials incorporated into the work, including transportation costs plus a restocking and/or handling fee not to exceed ten percent (10%) of the cost of the materials.
(5) All consultant fees associated with the public improvements at the invoiced amount plus administrative costs. Unless the amount totals less than Fifty Dollars ($50.00), the Village shall bill the Subdivider monthly for expenses incurred by the Village. Statements outstanding for more than thirty (30) days shall accrue interest at the rate of one and one-half percent (1-1/2%) per month. Bills outstanding for more than ninety (90) days shall be forwarded to the Subdivider's/Developer's surety agency for payment. Amounts less than Fifty Dollars ($50.00) shall be held for billing by the Village until amounts total more than Fifty Dollars ($50.00) or until the conclusion of project activities.
(e) Record Plans. After completion of all public improvements and prior to final acceptance of said improvements, the Subdivision, Condominium or Certified Survey Map Developer (as applicable) shall make or cause to be made one (1) Mylar and three (3) blue line copies of record plans showing the actual location of all improvements (unless manholes, stubs, sewer and water mains, etc.), and such other facilities as the Village Engineer shall require. These plans shall be prepared on the original mylars of the construction plans and shall bear the signature and seal of a professional engineer registered in Wisconsin. The presentation of the record plans shall be a condition of final acceptance of the improvements and release of the surety bond assuring their completion.