§ 53.114  CONTINUATION OF EXPIRED PERMITS.
   An expired user permit will continue to be effective until the permit is reissued only if: the user has submitted a complete permit application at least 90 days prior to the expiration date of the user’s existing permit (or at least 180 days prior to the expiration date of a five-year permit); and the failure to reissue the permit, prior to expiration of the previous permit, is not due to any act or failure to act on the part of the user; provided, however, in no case may a permit continue for a period of more than five years from the date of issuance. In all other cases, discharge to the POTW following expiration of a permit is unlawful.