Mechanical permit fees shall be charged according to the following schedule:
   (A)   Mechanical Permit Fees:
HVAC system:
New single-family dwelling
$100.00
 
New 2-family dwelling
150.00
 
New multi-family residence
100.00
plus $50.00 for each additional unit
Commercial and industrial building
50.00
plus 1 percent of material and labor
Miscellaneous service work on furnaces, duct work, air conditioning, etc., over $100.00
25.00
 
Furnace:
 
Up to 100,000 BTU
30.00
 
101,000 BTU and up
40.00
 
Suspended, recessed or floor mounted heaters
30.00
 
Installation or replacement of vents (chimney)
20.00
 
Repair, installation, or replacement of accessory furnace appliances and controls
20.00
 
Boilers:
 
To and including 100,000 BTU
30.00
 
101,000 BTU to and including 500,000 BTU
40.00
 
501,000 BTU to and including 1,000,000 BTU
42.00
 
1,001,000 BTU to and including 1,750,000 BTU
53.00
 
1,751,000 BTU and up
80.00
 
A/C units:
 
To and including 3 ton
30.00
 
To and including 15 ton
40.00
 
To and including 30 ton
42.00
 
To and including 50 ton
55.00
 
Over 50 ton
80.00
 
Ventilation (multiduct) other than heat or A/C
30.00
 
Ventilation fan (single duct) other than heat or A/C
25.00
 
Commercial hood type I or II
35.00
 
Installation or relocation of commercial incinerator
65.00
 
Gas piping system up to 4 outlets
20.00
 
Fireplace (gas or wood burning):
 
Fireplace new construction gas or wood
20.00
 
Other inspections and fees:
 
Inspections outside of normal business hours (minimum charge - 2 hours)
42.50
per hour1
Reinspection fees assessed under provision of section 116.6
42.50
per inspection1
 
Note:
1.   Or the total hourly cost to the jurisdiction, whichever is the greatest. This cost shall include supervision, overhead, equipment, hourly wages and fringe benefits of the employees involved.
   (B)   Plan Review Fees: When a plan or other data are required to be submitted by the mechanical code, a plan review fee shall be paid at the time of submitting plans and specifications for review. The plan review fees for mechanical work shall be equal to twenty five percent (25%) of the total permit fee as set forth in subsection (A) of this section. When plans are incomplete or changed so as to require additional plan review, an additional plan review fee shall be charged at the rate shown in subsection (A) of this section.
   (C)   Fee: An investigation fee, in addition to the permit fee, shall be collected whether or not a permit is then or subsequently issued. The investigation fee shall be equal to the amount of the permit fee that would be required by this code if a permit were to be issued. The payment of such investigation fee shall not exempt any person from compliance with all other provisions of this code nor from any penalty prescribed by law.
   (D)   Reinspections: A reinspection fee may be assessed for each inspection or reinspection when such portion of work for which inspection is called is not complete or when required corrections have not been made. (Ord. 07-05, 3-5-2007)