Unless specifically defined below, words or phrases used in this chapter shall be interpreted so as to give them the meanings they have in common usage and to give this chapter its most reasonable application.
APPEAL. A request for a review of the local administrator’s interpretation of any provision of this chapter or a request for a variance.
AREA OF SPECIAL FLOOD HAZARD. The land in the floodplain within the community subject to a 1% or greater chance of flooding in any given year.
BASE FLOOD. The flood having a 1% chance of being equaled or exceeded in any given year.
DEVELOPMENT. Any human-made change to improved or unimproved real estate, including, but not limited to, buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations located within the area of special flood hazard.
FLOOD or FLOODING. A general and temporary condition of partial or complete inundation of normally dry land areas from:
(1) The overflow of inland waters; and/or
(2) The unusual and rapid accumulation or runoff of surface waters from any source.
FLOOD INSURANCE RATE MAP (FIRM). The official map on which the Federal Insurance Administration has delineated both the areas of special flood hazards and the risk premium zones applicable to the community.
FLOOD INSURANCE STUDY. The official report provided in which the Federal Insurance Administration has provided flood profiles, as well as the flood boundary floodway map and the water surface elevation of the base flood.
HABITABLE FLOOR. Any floor usable for living purposes, which includes working, sleeping, eating, cooking or recreation, or a combination thereof. A floor used only for storage purposes is not a HABITABLE FLOOR.
LOCAL ADMINISTRATOR. The Director of City Services or his or her designee.
NEW CONSTRUCTION. Structures for which the “start of construction” commenced on or after the effective date of this chapter.
START OF CONSTRUCTION. The first placement of permanent construction of a structure on a site, such as the pouring of slabs or footings or any work beyond the stage of excavation. Permanent construction does not include land preparation, such as clearing, grading and filling, nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers or foundations or the erection of temporary forms; nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not as part of the main structure. For a structure without a basement or poured footings, the START OF CONSTRUCTION includes the first permanent framing or assembly of the structure or any part thereof on its piling or foundation.
STRUCTURE. A walled and roofed building, or a gas or liquid storage tank, that is principally above ground.
SUBSTANTIAL IMPROVEMENT.
(1) Any repair, reconstruction or improvement of a structure, the cost of which equals or exceeds 50% of the market value of the structure either:
(a) Before the improvement or repair is started; or
(b) If the structure has been damaged and is being restored, before the damage occurred.
(2) For the purposes of this definition, SUBSTANTIAL IMPROVEMENT is considered to occur when the first alteration of any wall, ceiling, floor or other structural part of the building commences, whether or not that alteration affects the external dimensions of the structure. The term does not, however, include either:
(a) Any project for improvement of a structure to comply with existing state or local health, sanitary or safety code specifications which are solely necessary to assure safe living conditions; or
(b) Any alteration of a structure listed on the National Register of Historic Places or a state inventory of historic places.
VARIANCE. A grant of relief from the requirements of this chapter which permits construction in a manner that would otherwise be prohibited by this chapter.